Ben Teh · IT Project Manager & Consultant · Kuala Lumpur
Projects that actually ship.
I keep the tech, the vendors and the deadline moving in the same direction — until it ships. Sixty-plus hotel network deployments across Southeast Asia, and a 700,000-item RFID programme in delivery right now.
Case 01
Sixty deployments, five countries, and one that opened with an earthquake.
Enterprise Wi-Fi and networking for Four Seasons, Hyatt and Banyan Tree across Malaysia, Thailand, Vietnam, Indonesia and Singapore. Different teams, different constraints, the same requirement: connectivity that never fails.
What I did
I ran the coordination layer between my team and the client's. I held the kick-off meetings that aligned both sides — what my team would deliver and watch out for, and how the hotel's people would accommodate and assist them.
Then I fronted the relationship with hotel IT managers and directors: chasing the missing information my team was blocked on, absorbing the complaints, running the UAT checklist and handover, and pushing sign-off through so finished work actually closed. Access point and hardware refreshes, gateway rollouts, firewall installs — many picked up mid-flight.
The hardest one
An earthquake hit on day one of the Thailand deployment. The schedule stopped being the point.
I got my engineers to safety and stayed in contact until I knew they were fine, then made sure the client's people were accounted for. Only after that did we go back for the equipment and rebuild the plan. With Songkran falling immediately after, I worked the timeline around both — and still closed the project before its deadline.
Case 02
Seven hundred thousand linen items, and a billing question nobody had asked.
A laundry operation tracking 700,000+ items was stuck with an incumbent system that couldn't deliver: poor read accuracy, no item-level counts, weak reporting, and instability that broke under 24/7 use.
What I did
Led the integration as a custom software house stepping onto unfamiliar RFID ground. Sourced and filtered vendors, then put shortlisted options to the client across three fronts: RFID hardware and installation, fabrication for the stations, and the PC hardware and peripherals around them.
Held the timeline and flagged risks early enough to head off costly mistakes before production. With the system nearly done the client swapped in an almost entirely new core operations team — so the job now is onboarding them onto decisions already made.
The find
One code shape carried two commercial services — and for half of them the system couldn't say how the stock was even counted.
HOTEL-DEPT-RENTAL
Linen the laundry ownsrented to the hotel
RFIDunambiguous
HOTEL-DEPT
Linen the hotel ownswashing only
RFID or hand-countedthe system doesn't record which — you had to ask operations
Rental and wash-only bill differently, so the same code meant two different invoices. I traced it, disproved the working assumption that a property is either all-RFID or none — one had 13 of 20-plus linen types tagged — and got a shared definition agreed across teams before the counts turned into invoices.
Proving it
The test plan arrived as an unsorted list of everything one engineer could think of.
I rewrote it into something a team could actually execute. The repeated steps got factored into named blocks, so the run reads as a short sequence instead of the same twenty lines copied out six times. The test site was built from two floors of a storage building — the upper one chosen precisely because passive scanning can't reach it. And the cycles were ordered so a billing report brackets a price change on both sides, which is the only way to find out whether new pricing quietly reaches backwards into work already invoiced.
I ran the first two cycles on the floor with the client's own operators, teaching them the flow rather than having my team drive it. My team running all six would prove the software works when experts use it. The client running the rest proves it works for the people who have to live with it.
Halfway through, it hit blockers. I put fixes to the team while we were still standing there rather than calling the day off, they landed, and the remaining cycles stayed testable. Every issue is logged and a second pass is scheduled once the fixes are in.
Meanwhile every request from the new operations team gets sorted before it gets scheduled: already asked, already built, or genuinely new. Only the third kind is a change.
Case 03
One hundred and seventy-one tests passed. The emergency stop was broken.
I ran a company through AI agents to find out whether one person could — and whether the whole thing would quietly go wrong. AI writes code fast, and confidently ships defects its own passing tests never catch.
What I did
Directed the build and owned the governance: executive core, human-approval gate, tamper-evident audit log, and a three-brain fallback ladder. I set direction, made the security calls, and acted as the verification layer — the AI wrote the code, I decided what was true.
Caught an emergency-stop control failing silently under load while 171 tests passed, and drove mutation testing that exposed a safety gate as effectively unguarded. Same job as managing vendors. The workforce just happens to be AI.
The person
The projects I want are the tangled ones: many parties, real consequences, no clean template.
A versatile IT professional with a Master of Information Technology, working across project management, data analytics and software development. What clients tend to remember is that I spot problems early, keep multiple vendors pulling in the same direction, and hold the line on scope, timeline and quality — from kickoff through to handover.
Track record
Project Consultant
Ez Edtech Solutions Sdn Bhd
Project Engineer
LinkBroad Technology (M) Sdn Bhd
Data Analyst
Hotayi Electronic (M) Sdn Bhd
Head of Digital Transformation and Innovation
Australian Malaysian Singaporean Association
Previously Head of Offshore Engagement, 2025–26 · Head of Membership, 2023–25
IT Administrator
Nan Tien Temple
A rollout that needs a steady hand, or a vendor maze that needs untangling.
Based in Kuala Lumpur, working across Southeast Asia. WhatsApp is the fastest way to reach me.